18MW Turnkey Data Dentre , Dublin, Ireland

DCIM100MEDIADJI_0017.JPG

IMG_0200 IMG_0193

 

 

 

 

 

 

 

Winthrop were appointed by a Private U.S Client as Main Turnkey Contractor for this project in Grange Castle Dublin, with construction having commenced in October 2016.

With planning having been successfully approved in September 2016, Winthrop had already engaged in the development process several months prior, aligning key elements for the project delivery.

The complete site was a concrete scaffold yard, which had to be broken up and brought back to a brown field site.

The project is being delivered over 2 Phases, with both Phases to be complete by mid 2017
Phase 1: 8MW
Commenced in October 2016 and will be completed by June 2017 ( Delivered in 9 Months)
Phase 2: 10MW
Commenced January 2017 and will be completed by September 2017 (Delivered within a further 3 months)

Total delivery time for 18MW  from a Concrete based site: 12 Months