43MW Data Centre, Amsterdam, Holland

AMS Pic 2

AMS Pic

 

 

 

 

 

 

In late 2015, Winthrop were engaged by a US Client to deliver a rollout of turnkey Data Centres across Europe. The overall project consists of several facilities across various locations in Europe, beginning with Amsterdam as detailed below.

Winthrop are acting as overall contractor with a design assist role.

Phase 1.1: 4MW
Commenced: November 2015 & Completed: June 2016
Phase 1.2: 4MW
Commenced: October 2016 and will be completed by May 2017
Phase 2.1: 10MW
Commenced April 2016 & completed November 2016
Phase 2.2: 10MW
Commenced September 2016 and will be completed by June 17
Phase 3.1: 10MW
Commenced 2016 and will be completed by September 2017
Phase 3.2: 5MW
Commencing March 2017 and will be completed by November 2017

Key Points: This project is a complex reconfiguration of existing buildings, thus maximising usage of site space. This includes double stacking of external equipment, and accommodating 10MW of IT Load into 30,000 sq/ft of Data Hall space