UPS Office HQ, Dublin

20140612_105945_800 20140612_110009_800

The proposed works consist of office fit-out of existing building on Ground & First Floor with associated M&E works in roof level plant rooms.

Works to include:
•    Stud walls to provide meeting rooms/training rooms
•    Additional toilet/shower facilities
•    Break-out rooms, suspended ceilings, installation of workstations and office furniture and associated data/power wiring and all associated drainage
•    New carpet to raised access floor
•    Additional air conditioning and lighting upgrades

SCOPE OF WORKS:  M&E Fitout Contractor
VALUE: €1,800,000
DURATION: 3 Months

PROJECT TEAM
ARCHITECT: David Gilligan Architects
CONSULTING ENGINEER: J V Tierney
MAIN CONTRACTOR: Winthrop Engineering