↑ Return to Mission Critical

Interxion Data Centre’s Phase’s 1,2,3,5, Dublin

interxion01 interxion02 interxion03 interxion04 interxion05 interxion06

Works include:
Winthrop was commissioned to deliver an overall M & E Design & Build solution for Interxion. This fast track programme was planned across 4 Phases to ensure programme timelines were met in a timely and cost effective manner. Phases 1, 2, 3 & 5 are complete. Phase 4 is yet to commence.
Project Summary: P1 & P2 Construction of 4 no. Data Halls & Plant. P3 Additional Capacity in existing Data Halls, P5 Extension to Data Centre, 2 New Data Halls and significant additional plant. All plant was selected on an N + 1 basis, with N + N for the UPS. Fully detailed Integrated System Testing (I.S.T.) planned & executed.

 

SCOPE OF WORKS:  Mechanical & Electrical Design & Build Subcontract
PROJECT VALUE: €14m  – Phase 1,2,3,5
DURATION: 3 Months
SIZE: All Phases 2400sqm at 1.5kW/sqm

PROJECT TEAM
CONSULTING ENGINEER: Ethos Engineering (for Winthrop)
MAIN CONTRACTOR: StructureTone Limited