Pallas Foods, Dublin

V_1_800downloadPallas Foods Truck Rear after No-H2O 1_1

New Build of 39,000sqm Food Distribution Centre

Works to include:

Winthrop have completed  the mechanical and electrical services on the new Refrigerated and Dry Goods Distribution Centre which was designed & built by the team to the clients particular requirements. Notable services include:

•    MV substation
•    Roof mounted gas ired AHU’s
•    Bespoke warehouse lighting scheme
•    Vehicle maintenance building for client fleet of trucks

The facility comprises of Dry goods warehouse, Dry dock, Freezer warehouse, Cold dock, vehicle maintenance facility and an office building

SCOPE OF WORKS: Mechanical & Electrical Services

SECTOR: Industrial
CLIENT: John Paul Construction
PROJECT VALUE: €14.5 million
DURATION: 12 Months

PROJECT TEAM
ARCHITECT: O’Toole Partnership
CONSULTING ENGINEER: Ethos Engineering
QUANTITY SURVEYOR: John Paul Balfour Beatty
MAIN CONTRACTOR: John Paul Balfour Beatty