↑ Return to Medical

Coombe Hospital, Dublin

001_coombehospital_800 002_coombehospital_1_800 003_coombehospital_800

Winthrop were awarded the Mechanical Services Installation for the new emergency theaters & delivery suites contract in the Coombe hospital.

Works to include new installation and refurbishment works to
•    HVAC services & plant
•    Soils & Wastes
•    Gas Boilers & Heating Services
•    Water services
•    Medical Gases
The project consists of the installation of mechanical services to the new unit including refurbishment & upgrade works to the existing mechanical services infrastructure. The total installation of mechanical services will cover approximately 2,100 sq metres and works will be completed in accordance with HTM’s standards and local hospital technical requirements. The works will be carried out in live occupied areas and in the new two storey facility. To facilitate the refurbishment works and to enable service diversions and connections to other areas of the hospital the project will be carried out over a number of phases.

SCOPE OF WORKS: Mechanical Services
VALUE: €800,000
DURATION: 12 Months

PROJECT TEAM
ARCHITECT: RKD
CONSULTING ENGINEER: Ethos Engineering
QUANTITY SURVEYOR: RKD
MAIN CONTRACTOR: Clancy Construction