MSD – Bio Pharma, Switzerland

Description of Works

Winthrop worked with the FESP as a liaison with the client and their design team. Services comprised of the extension of existing facilities to service new warehouse and a Weigh and Dispense Facility. Detailed construction drawings were developed by Winthrop, which allowed for extensive prefabrication off-site. Systems worked on included steam, chilled water & compressed air including tie-ins to live client systems. Client protocols for the production, construction, handover, commissioning and validation of full documentation for each stage were incorporated into Winthrop’s subcontract scope.

Scope of Works

Mechanical / Process Services

Project Value

€1,750,000

Duration

3 Months

Architect

Burckhardt & Partners

Consulting Engineer

ARUP

Main Contractor

Winthrop Engineering

Category

Pharmaceutical