Winthrop were commissioned by the Client to deliver an operational Data centre within an extremely challenging timeframe. The existing premises was converted to 3 floors of Data hall at 1296sqm/floor and adjacent 2,376 sqm Warehouse converted into M & E Plantrooms. Plant was selected on an N+ 1 Basis with UPS on an N + N. Objective was to achieve Tier IV compliance. Client required design & costing for full scale project. Winthrop then developed a phased build-out strategy to align with commercially viable Phases to suit Client funding plans. Security measures included electric gates, bollards, hand biometric scanners, IP presence detection CCTV.
Mechanical & Electrical Contractor
€ 5,500,000
9 Months
McArdle MacSweeney Associates
Winthrop Engineering
Mission Critical