Vaasa, Finland, 2x96MW

Client:  Global Lease Provider

Capacity:   2 x 96MW

Scope:  Turnkey (PCSA, Early Works, CSA, MEP, Cx)

Floor Area:    38,500 m2

 

Project Features:

  • 2 Data Centres on Campus
  • Data Centres are each 2-storeys
  • Piled foundations to data centers, rock blasting required to southern portion of site
  • Steel frame building
  • Zero generator electrical design
  • Data Centre cooling is a mixture of air and liquid with a provision to adapt to 100% liquid cooling in the future

 

Start Date:  March 2026

 

 

 

 

Category

Current, Mission Critical