Worldcom, 3MW

Description of Works

Winthrop provided the mechanical services to WorldCom MKI IDC facilities in Erne Street, and Clonshaugh Dublin. Both projects were fast tracked by the off site prefabrication of pipework in order to minimise site install time and reduce the mechanical construction programme.

Scope of Works

Mechanical Contractor

Project Value

€4,500,000

Duration

7 Months

Consulting Engineer

McArdle MacSweeney Associates

Main Contractor

Pattons Ltd.

Category

Mission Critical